Largest hydroelectric power plant in Central Asia

24. August 2018

 

International technology Group ANDRITZ is refurbishing and modernising the largest hydropower plant in Central Asia, in the Republic of Tajikistan. With a current output of 3,000 MW, it covers more than 70% of the national electricity demand. After installing the new 380 MW Francis turbines and generators, the power plant will have an additional 12% installed capacity. An essential part of the € 120 million contract is also taking into account the requirements for environmental protection and water management.


 

ANDRITZ to modernize the largest hydropower plant in Central Asia

 

International technology Group ANDRITZ has received an order from Barqi Tojik, Tajikistan, for rehabilitation and modernization of the entire electro-mechanical equipment, including the inspection and repair of nine penstocks, for the existing Nurek hydropower plant in the Republic of Tajikistan. With the current installed capacity of 3,000 MW, Nurek is the largest hydropower plant in Central Asia and covers more than 70% of the national electrical energy demand. The project is funded by the World Bank. The contract value for ANDRITZ amounts to slightly more than 120 million euros. The objectives of the Nurek Hydropower Rehabilitation Project for Tajikistan are to rehabilitate and restore the generating capacity of nine power generating units at Nurek hydropower plant, improve their efficiency, and enhance the safety of the Nurek dam.

The ANDRITZ scope of supply comprises comprehensive modernization of the existing nine generating units by supplying and installing new 380 MW Francis turbines and generators, including new transformers, as well as the electrical and mechanical auxiliary equipment within the power house. After modernization, the installed capacity of the generating units will be increased by about 12%.

The design of the new units takes account of the plant’s annual storage operations and will, therefore, be suitable for operation with a wide range of heads. Together with the Rogun hydropower plant, which is under construction and located upstream of the Nurek reservoir, this project will optimize water storage management on the Vaksh river cascade, ensuring a significant increase in electrical energy production by the Nurek hydropower station as well as meeting the changing grid demands. The contract also stipulates that environmental conservation measures and water management requirements must be incorporated.

The rehabilitation of Nurek will safeguard the electrical energy supply in the Republic of Tajikistan and make an important contribution towards the strategic use of renewable energy from hydropower in Central Asia. It also offers interesting opportunities for exporting energy to neighboring countries, with the related economic benefits for the countries concerned. The award of this contract further strengthens ANDRITZ’s market position in the important region of Central Asia.

 

Weitere News zu diesem Thema

China orders Styrian hydropower plants

ANDRITZ has received an order for the supply of four 350 MW reversible pump turbines and motor generators from China. More →


New life for used batteries

The "Second Life" project, which is part of the Green Energy Lab, deals with the reuse of already used batteries from electric mobility. More →


Opening of the unique Green Tech Hub

As a unique project in Austria, the new Green Tech Hub was opened in the Science Tower in Graz. On more than 400 m² it offers ideal conditions for growth and development especially for companies and start-ups who are active in the field of green technology. More →